Skip to content
MaintWiz: Innovating Industrial AI

Calculators

Shutdown Calculators: Delay, Scope, KPIs and Time on Tools

Short answer

This page lists the 18 free shutdown calculators on MaintWiz guides, grouped by schedule, cost and value, and scope, readiness and safety. Each runs in your browser on your own numbers and sits on the guide that explains its method.

Starting values in every calculator are invented placeholders. Nothing you enter is sent or stored.

How MaintWiz helps: Calculators answer one question; a live plan answers them all. The MaintWiz shutdown module puts the whole shutdown on a Gantt chart with the critical path, float and baselines, so you can see what moves the finish date. See the module · Get the Gantt template

By · Published · Last reviewed

What MaintWiz adds:Gantt with critical path and floatBaselines show what movedFloat flag at your limitOne plan from portfolio to task

Schedule

Which shutdown schedule calculators are there?

The schedule calculators work out float, the critical path, the effect of a slip, the finish forecast, the backward plan from a start date, the latest order date for a part and the next shutdown date.

Schedule terms follow the US GAO schedule guide: float is how long an activity can slip without delaying a later date, and the critical path is the longest continuous sequence of activities. 1

Schedule calculators
CalculatorYou enterResult shownWhere it lives
Compute total floatEarly start (day); Duration (days); Late finish (day)Early finish; Late start; Total float; StatusParent guide
Change a duration and watch the critical path moveThe activity durations of the worked example (editable)Job duration, days; Zero-float activitiesParent guide
How far does one late job move the finish?Total float of the job, days; Slip of the job, daysDelay to the finish date, days; Float left, days; StatusParent guide
Forecast the finish from today's progressPlanned duration, days; Planned progress today, %; Actual progress today, %Progress variance, points; Progress ratio (actual / planned); Forecast duration, days; Days late at this paceParent guide
Put your start date into the backward planShutdown start date; Scope approved: weeks before start; Plan and schedule baselined: weeks before start; Scope frozen: weeks before start; Readiness review: weeks before startScope approved; Plan and schedule baselined; Scope frozen; Readiness reviewParent guide
When is the latest order date?Shutdown start date; Supplier lead time, weeks; Transit and customs, days; Inspection and buffer, daysTotal lead time, days; Latest order dateParent guide
When is the next shutdown due, and when must planning start?Last shutdown ended; Interval, months; Planning lead time, monthsNext shutdown due; Planning should start byParent guide

Cost and value

Which shutdown cost calculators are there?

The cost calculators compare planned and unplanned cost, overrun against contingency, the cost of delay, program ROI and the shutdown KPIs.

The cost calculators use the standard definitions of earned value measures where they apply. 2 Every starting value is an invented placeholder: replace it with your own figures.

Cost and value calculators
CalculatorYou enterResult shownWhere it lives
Planned versus unplanned cost of the same jobMargin lost per hour; Planned downtime, hours; Unplanned downtime, hours; Repair cost if planned; Repair cost if unplanned; Premiums and expedite cost if unplannedPlanned total; Unplanned total; Difference; Unplanned as a share of plannedParent guide
Overrun and contingency usedBaseline budget (excluding contingency); Contingency held; Forecast or final costOverrun against baseline; Against authorized budget (baseline + contingency); Contingency usedParent guide
Cost of delayLost margin per day; Crews and equipment kept on site, per day; Site services that continue, per day; Days of delayCost of one extra day; Cost of the delayParent guide
A worked ROI with your own numbersDays of downtime avoided; Value of one production day; Other yearly benefits (rework, overtime, parts); Total program cost for the yearYearly benefit; Net benefit; ROI; PaybackParent guide
Shutdown KPI calculatorBudget at completion (BAC); Planned value to date (BCWS); Earned value to date (BCWP); Actual cost to date (ACWP); Planned duration, days; Actual or forecast duration, daysCost variance; Cost performance index; Schedule variance; Schedule performance index; Estimate at completion; Duration variance; Scope growth; Recordable injury rateParent guide

Software

When is a calculator not enough?

A calculator answers one question from numbers you type; a shutdown module keeps the schedule, cost, permits and spares as live records, so the answers update as the work does.

About MaintWiz. MaintWiz is an industrial AI platform with IoT, SAP integration and predictive maintenance (PdM) capabilities. Its shutdown and turnaround module helps plants plan, schedule, execute and close out shutdown work.

What the shutdown module covers

As described on the MaintWiz shutdown maintenance product page.

  • Calculators on this page are free tools, not part of the shutdown module
  • The module computes the critical path, float and baselines from your real schedule
  • Earned value: planned, earned and actual cost with the cost and schedule indices
  • Spares status with the SAP request or order behind each short part
  • Reports and the tables behind the charts export to Excel

Scope, readiness and safety

Which scope, readiness and safety calculators are there?

These calculators measure scope growth, work package readiness, risk score, checklist progress, time on tools and the permit issuers needed on a peak day.

Scope, readiness and safety calculators
CalculatorYou enterResult shownWhere it lives
Scope growth by sourceFrozen scope; Emergent work added; Discovery work added; Approved late requests; Work removed or deferredFinal scope; Net scope growth; Share from discovery; Share from late requestsParent guide
Is your work package ready?Ticks against ten readiness testsReady items; VerdictParent guide
Score a riskLikelihood; SeverityScore; BandParent guide
How far along is your checklist?Ticks against the 40 stepsSteps closed; Phase 1; Phase 2; Phase 3; Phase 4; Phase 5Parent guide
Time on toolsHours on site; Waiting for permits or isolations; Waiting for materials or tools; Travel, gear-up and breaks beyond plan; Other lost hoursHands-on hours; Time on tools; Largest lossParent guide
How many permit issuers do the peak days need?Permits on a peak day; Issuer minutes per permit (issue, checks, close); Productive minutes per issuer per shiftIssuer hours needed; Issuers neededParent guide

Using them

How do the shutdown calculators work and what are their limits?

Each shutdown calculator runs in your browser on the numbers you enter, starts with invented placeholder values and sits on the guide that explains its method, so read the guide before you rely on a result.

More free tools are listed in free shutdown planning tools.

How the calculators work
QuestionAnswer
Is my data uploaded?No. Each calculator runs in your browser; nothing is sent or stored
Are the starting numbers real?No. They are invented placeholders from a worked example; replace them with your own
Where is the logic?On the parent guide, next to the method it supports; this page does not duplicate it
Can I trust a result?It is only as good as your inputs; read the caution on the parent guide, and check the sources it cites

For a tool that turns a task list into a Gantt chart with a critical path, see the Excel to Gantt tool.

Definitions

Which definitions do the shutdown calculators use?

The calculators use public definitions: critical path and float from the HHS and GAO guides, the earned value measures from the HHS and GAO glossaries and guides, and the injury rate from the US Bureau of Labor Statistics. 3,1,2,4

Definitions behind the calculators
MeasureDefinitionSource
Critical pathThe path through a network of dependent tasks with the longest elapsed time; it sets the shortest possible durationHHS earned value glossary
FloatThe time an activity can slip without delaying a later date; float is not contingencyGAO schedule guide
Cost variance and cost performance indexCV is earned value minus actual cost; CPI is earned value divided by actual costHHS earned value glossary
Schedule variance and schedule performance indexSV is earned value minus planned value; SPI is earned value divided by planned valueHHS earned value glossary
Estimate at completionActual cost to date plus the current estimate to complete; the GAO guide gives EAC = ACWP + (BAC - BCWP) / efficiency indexHHS earned value glossary, GAO cost guide
Recordable injury (incidence) rateCases x 200,000 / hours worked (BLS example: 7 cases in 400,000 hours = 3.5)BLS incidence rate

Check the source for the full definition. The time-on-tools, scope growth and permit issuer calculations are working methods explained on their guides, not published standards.

Visuals

Save the calculator charts

Two charts to share with your team. Click either for the full-size image.

FAQ

Frequently asked questions

How do I calculate the cost of one extra shutdown day?

Use the cost of delay calculator on the budget guide: enter your own daily figures; the starting values are invented.

How do I calculate time on tools?

Use the time on tools calculator on the contractor guide: hours on site and hours lost to waiting.

How do I calculate the latest order date for a long-lead part?

Use the latest order date calculator on the spare parts guide: shutdown start date and the supplier lead time.

How do I calculate scope growth?

Use the scope growth calculator on the scope guide: the frozen scope and what was added or removed after.

How do I calculate the next shutdown date?

Use the next shutdown calculator on the timing guide: the last shutdown date, the interval and the planning lead time.

How many permit issuers do I need?

Use the permit issuer calculator on the permit guide: permits on a peak day and the time each takes.

Is my data uploaded?

No. The calculators run in your browser; nothing is sent or stored.

How many calculators are there?

18 across the shutdown guides, grouped above.

Put your shutdown schedule in one plan

Book a demo and bring your shutdown schedule. We will show how the module handles the critical path, float and baselines.

Book a demo