Skip to content
MaintWiz: Innovating Industrial AI

Shutdown checklist

Shutdown Checklist: 40 Steps for a Safe Plant Shutdown

Short answer

A shutdown checklist is an ordered list of the controls a plant needs before, during and after a stop: frozen scope, packaged work, staged materials, controlled isolations and permits, and a safety review before restart. Each of the 40 steps below has an owner, a timing and the evidence that closes it.

Owners and timings are typical working assumptions; adjust them to your organization and the size of the stop.

How MaintWiz helps: A checklist in a spreadsheet does not tell you what is blocked. The MaintWiz shutdown module moves the plan from spreadsheets into one system with a critical path, readiness gates, permits and spares status. See the module · Get the 40-step checklist

By · Published · Last reviewed

What MaintWiz adds:Critical path and floatReadiness gatesPermits and isolationsSpares status with SAP

The structure

How is the 40-step shutdown checklist organized?

The checklist has five phases, from scope and strategy to close-out and review, and each of its 40 steps names an owner, a timing and the evidence that closes it, so progress can be checked rather than assumed.

A gated version of these phases is shown in T&I turnaround and inspection planning.

This checklist covers the work of shutdown maintenance from the first planning decision to the review after restart. It has 40 steps in five phases. Every step has a typical owner, a timing and the evidence that closes it. A step is not done until its evidence exists.

The five phases of the 40-step shutdown checklist
PhaseStepsThe question it answersIt ends when
1. Scope and strategy1 to 8What is in, why, and by when?The baseline scope is frozen and the critical path is known
2. Plan and schedule9 to 16Can the work be done in the window?Packages, schedule, people and materials are confirmed
3. Readiness17 to 23Is the plant safe and ready to start?The readiness review records a go
4. Execute and restart24 to 38Are we still on the path to a safe restart?The pre-startup review is signed and the plant restarts in sequence
5. Close-out and review39 to 40What did the stop teach us?Post-startup results and lessons update the plans

The phases are the same five used across the MaintWiz shutdown guides. Owners and timings are working assumptions that fit a typical process plant; change them to match your organization and the size of your stop. There is no published standard that fixes the number of steps.

Phase 1 · Scope and strategy

What are the steps in phase 1, scope and strategy?

Phase 1 settles why the plant is stopping, when, and exactly what work is in: define the objective and window, build one controlled scope, learn from the last stop, rank the equipment and freeze the baseline.

Steps 1 to 8 with owner, timing and evidence
DoneStepOwner (typical)WhenEvidence that closes it
1. Define the objective
State why the stop happens (statutory inspection, overhaul, reliability work, modification) and the measurable outcomes, such as a safe restart, compliance work complete or no critical punch items.
Plant managerStart of planningSigned objective statement
2. Set the window
Fix the start and finish dates, the operating constraints and the restart deadline.
Operations managerStart of planningApproved window
3. Build one master scope
One controlled register of all approved work: work orders, inspections, statutory work, modifications, cleaning, deferred and opportunity work. No side lists in spreadsheets and email.
Shutdown managerEarly planningScope register with one owner
4. Review the last shutdown
Check deferred jobs, recurring failures, inspection findings, overruns, contractor and material issues and startup problems, and carry them into the scope.
Shutdown managerEarly planningLessons carried into scope
5. Rank equipment by criticality
Rank by consequence of failure, safety exposure, production impact, environmental risk, redundancy, repair complexity and regulatory importance.
Reliability engineerEarly planningCriticality ranking
6. Validate the work orders
Each has a description, asset, scope, duration, craft, safety and material needs and completion criteria.
PlannerBefore the scope freezeComplete work order set
7. Freeze the baseline scope
Set a freeze milestone. After it, additions need written approval with a safety, compliance, reliability or production reason. 1
Shutdown managerScope-freeze milestoneApproved baseline and open change log
8. Identify the critical path
Map the dependencies and find the activities that set the restart date, so management attention goes where a delay moves the finish. 1
SchedulerAfter the freezeNetwork and critical-path list

Scope that is found during the stop costs more than scope that is found in planning. See the scope management guide for the freeze date and for emergent work.

Software

Can software run the shutdown checklist?

A spreadsheet can hold the 40 steps, but it cannot link them to the schedule, the work orders, the permits and the spares; software can keep each step tied to its evidence and show which open step blocks the restart.

See the shutdown module FAQ and shutdown software vs CMMS vs Primavera P6 before choosing a tool. See the turnaround software checklist before you choose a tool.

About MaintWiz. MaintWiz is an industrial AI platform with IoT, SAP integration and predictive maintenance (PdM) capabilities. Its shutdown and turnaround module helps plants plan, schedule, execute and close out shutdown work.

Also see the work package guide.

What the shutdown module covers

As described on the MaintWiz shutdown maintenance product page.

  • Gantt chart with critical path and float, so step 8 stays live as work changes
  • Readiness gates for each work package, with waivers and sign-offs recorded with a reason, the name and the date
  • Work orders with tick, reading and photo tasks; findings go to the planner as requests for added work
  • Spares status with the SAP request or order behind each short part
  • Permits and isolations from ePTW shown on each work order
  • Import and export with Excel
  • Approvals recorded against the signed-in user with the name and the time
  • QR code scan and offline use on transaction screens

Phase 2 · Plan and schedule

What are the steps in phase 2, plan and schedule?

Phase 2 turns the frozen scope into field-ready work packages, a logic-linked schedule, confirmed people and contractors, and materials that are physically on site.

Long-lead parts are covered in shutdown spare parts planning. In SAP, see SAP MM shutdown materials for reservations and requisitions.

Steps 9 to 16 with owner, timing and evidence
DoneStepOwner (typical)WhenEvidence that closes it
9. Develop work packages
Each package holds the job steps, tools, materials, drawings, procedures, permits, manpower, duration, inspection points and acceptance criteria.
PlannerAfter the freezeField-ready packages
10. Validate the estimates
Review hours and durations with planners, supervisors and technicians, using historical actuals where they exist.
Planner and supervisorsAfter packagingReviewed estimates
11. Sequence the work
Order isolation, cleaning, inspection, dismantling, repair, testing, reassembly and commissioning, and link each activity to its predecessors. 1
SchedulerDuring schedulingLogic-linked schedule
12. Confirm drawings and procedures
Current P&IDs, equipment and electrical drawings, inspection procedures, torque specifications and vendor documents for every package.
EngineeringBefore the readiness reviewDocument set per package
13. Screen changes for management of change
Any change to design, process conditions, controls, materials or operating procedures goes through the site’s management of change process. 6
EngineeringBefore the freeze and on every changeManagement of change records
14. Confirm the workforce
Trades, inspectors, scaffolders, riggers, engineers, planners, supervisors and safety staff, with shifts, weekends, fatigue, competence and cover. 1
Shutdown managerAfter schedulingResource-loaded plan
15. Mobilize contractors early
Choose on capability, safety performance, availability, certification and shutdown experience, and confirm capacity before the window, not during it. 6,7
Contracts managerBefore the stopContracts and mobilization plan
16. Confirm long-lead materials
Identify parts that could stop the critical path and check they are physically received, not only ordered.
Materials plannerBefore the stopMaterial readiness report

The scheduling guide shows how to find the critical path and float, and the spare parts guide covers long-lead items and kitting.

Phase 3 · Readiness

What are the steps in phase 3, readiness?

Phase 3 makes sure the plant is safe and ready before the first permit is issued: risks, isolations, permits, contractor induction, simultaneous work and a formal go or no-go.

Steps 17 to 23 with owner, timing and evidence
DoneStepOwner (typical)WhenEvidence that closes it
17. Build the risk register
List technical, safety, environmental, schedule, material, contractor, quality and restart risks. For each major one record the trigger, the preventive control, the owner and the contingency.
Shutdown managerBefore the readiness reviewRisk register
18. Confirm the isolation approach
List every energy source to isolate: electrical, mechanical, hydraulic, pneumatic, thermal, chemical, pressure, gravity and stored energy. Plan intrusive work for the stop to keep isolation needs down. 2
Operations and safetyBefore the stopIsolation plan
19. Verify lockout requirements
Define lockout and tagout, or the site equivalent, for each item, including group lockout and the exchange of procedures between host and contractors. 4
SafetyBefore the stopLockout procedures
20. Prepare the permit requirements
Decide which jobs need hot work, confined space entry, line breaking, electrical, work at height, excavation, lifting, radiation or chemical handling permits. 3,5,6
Permit coordinatorBefore the stopPermit matrix by package
21. Induct the contractors
Cover site rules, emergency arrangements, restricted areas, protective equipment, the permit process, reporting and stop-work authority. 6
SafetyAt mobilizationInduction records
22. Plan simultaneous operations
Map jobs that could affect each other: hot work near chemical cleaning, lifting near energized work, scaffolding near operating equipment, confined space entry beside other work.
Shutdown manager and safetyBefore the peakSimultaneous operations plan
23. Hold the readiness review
Check scope, people, materials, permits, equipment, procedures, logistics, safety controls and communication, and record a go or no-go for each major work front.
Shutdown managerBefore the stopSigned go or no-go record

Permits, isolations and lockout are covered in the permit to work guide and the safety plan guide.

Phase 4 · Execute and restart

What are the steps in phase 4, execute and restart?

Phase 4 runs the stop day by day and then brings the plant back: controlled shutdown, daily control, quality hold points, then completion checks, testing, a safety review and a staged restart.

Float and the critical path: critical path vs critical chain. Restart in regulated plants: pharmaceutical plant shutdowns.

Execution and daily control: steps 24 to 31

Steps 24 to 31 with owner, timing and evidence
DoneStepOwner (typical)WhenEvidence that closes it
24. Shut down under control
Follow the approved sequence. Hand equipment to maintenance only after isolation, depressurizing, draining, cleaning, purging and verification are complete.
OperationsDay of shutdownHandover-to-maintenance record
25. Set up the control room
One control point for the schedule, work-front status, safety, critical path, resource conflicts, shortages, scope changes, quality and restart readiness.
Shutdown managerDay of shutdownControl room running
26. Hold the daily meeting
Short and decision-oriented: planned against actual, critical path, safety events, permits, shortages, contractors, quality holds, new scope and recovery actions. 8
Shutdown managerEvery dayMinutes and actions
27. Track progress against the baseline
Measure completed work, inspection sign-offs and test records, not percent-complete estimates alone. 1
SchedulerEvery dayProgress report against the baseline
28. Control emergent work
Judge each finding by safety consequence, regulation, production risk, reliability, restart risk, time and resources, then approve, defer or reject it in writing.
Shutdown managerAs findings appearDecision log
29. Protect the critical path
When a critical task slips, start recovery at once: extra shifts, resources moved, work resequenced, specialists, parallel work or material escalation. 1
Shutdown managerWhen a critical task slipsRecovery plan
30. Hold quality hold points
Set inspection and acceptance points for critical work, so equipment moves from repair to inspection, testing, acceptance and reassembly only with evidence.
Inspection leadPer packageSigned inspection records
31. Keep a live punch list
Record incomplete or defective work as it appears and classify each item by its effect on safe startup. A list started at the end signals weak completion control.
SupervisorsEvery dayClassified punch list

Testing, commissioning and restart: steps 32 to 38

Steps 32 to 38 with owner, timing and evidence
DoneStepOwner (typical)WhenEvidence that closes it
32. Verify mechanical completion
Confirm reassembly, inspections, torque checks, lubrication, guards, supports, alignment and documentation.
Maintenance leadBefore testingMechanical completion records
33. Complete the pressure and functional tests
Pressure, leak, electrical, instrument, control-loop and system tests, recorded and traceable.
Commissioning leadBefore restartTest records
34. Verify blinds and isolations
Keep a controlled record of blinds, blanks, isolations, temporary connections and removed protections, and verify the approved configuration before re-energizing or pressurizing. 2
Operations and safetyBefore re-energizingClosed isolation and blind register
35. Walk down the systems
Operations, maintenance, engineering and safety check for loose tools, foreign objects, open drains, wrong valve positions, missing guards, temporary hoses, unconnected instruments, unfinished insulation and wrong electrical connections.
OperationsBefore startupWalkdown sheets
36. Close the critical punch items
Verify startup-critical items before authorization. Give every other item an owner and an approved post-startup plan.
Shutdown managerBefore startupPunch list closure record
37. Run the pre-startup safety review
A formal review of technical completion, safety controls, procedures, training, documentation, alarms, interlocks, emergency systems and operating readiness. 6
Operations manager and safetyBefore restartSigned review
38. Restart in the approved sequence
Bring systems back in order, not all at once, and watch equipment closely during the first operating period. 9
OperationsRestartRestart log

For the daily routine see the progress tracking guide, and for change control and handover see the execution guide. The restart checks are explained in the start-up guide.

Phase 5 · Close-out and review

What are the steps in phase 5, close-out and review?

Phase 5 checks that the plant stays healthy after restart and turns what the stop taught you into better plans for the next one.

Steps 39 to 40 with owner, timing and evidence
DoneStepOwner (typical)WhenEvidence that closes it
39. Monitor post-startup performance
Track temperature, vibration, pressure, flow, energy use, quality, alarms, repeat failures and production stability. Some defects only show once equipment runs.
Reliability engineerFirst days and weeks after restartPost-startup report
40. Capture the lessons and update the plans
Review schedule, cost, safety, scope growth, contractors, materials, inspection findings, repeat failures, startup problems and planning accuracy. Then update asset history, maintenance plans, job plans, checklists, risk registers, spares strategy and the scope of the next stop.
Shutdown manager and reliability engineerAfter restartLessons report and updated plans

The measures to report are in the KPI guide.

Rules

Which checklist steps do US and UK rules address?

No rule requires this exact checklist, but nine groups of steps are backed by US or UK rules or guidance, including management of change, contractor control, isolation and lockout, permits, shift handover and the pre-startup safety review. 6,2,4

The pre-shutdown shutdown audit checks these steps. Gate reviews at T-90 and T-30 days are covered in turnaround readiness review and phase gates.

Checklist steps that US and UK rules or guidance address
StepsRule or guidanceWhat it saysSource
7, 8, 11, 14, 27, 29GAO schedule assessment guideDescribes the baseline, the critical path as the longest continuous sequence of activities, float, and the resource-loaded schedule. The guide is for US federal programs and is used here as a general scheduling reference.GAO schedule guide
13OSHA 1910.119(l), US covered processesRequires written procedures to manage changes, except replacements in kindOSHA 1910.119
15, 21OSHA 1910.119(h) and HSE contractor guidanceThe host employer evaluates contractor safety performance, informs contractors of hazards and controls their presence; the contractor trains its people. HSG159 sets out how to manage contractorsOSHA 1910.119, HSE HSG159
18, 34HSE HSG253, safe isolationPlan intrusive maintenance for shutdown periods to keep isolation needs down; a blank and blind register is among the controls that assure full reinstatementHSE HSG253
19OSHA 1910.147, control of hazardous energyHost and outside employers inform each other of their lockout or tagout procedures; group lockout and tagout is coveredOSHA 1910.147
20HSE HSG250; OSHA 1910.146 and 1910.119(k)Permit-to-work systems; an entry permit documents the measures taken before confined space entry; a hot work permit documents fire prevention and protection on a covered processHSE HSG250, OSHA 1910.146, OSHA 1910.119
26HSE shift handover guidanceHandover has three elements: preparation, an exchange between outgoing and incoming staff, and a cross-checkHSE shift handover
37OSHA 1910.119(i), US covered processesA pre-startup safety review applies to new facilities and to modified facilities when the modification changes the process safety information. Using the same review after maintenance is a site choiceOSHA 1910.119
38US CSB, BP Texas CityThe 2005 explosions occurred during the restarting of a hydrocarbon isomerization unitCSB Texas City report

Progress

How do you know the checklist is on track?

Count a step as closed only when its evidence exists, and watch the phase counts rather than one overall percentage, because a late phase 1 or phase 3 step blocks everything after it.

A free Excel version of the checklist, with a progress count by phase, is in the shutdown planning templates. The Excel to Gantt tool turns your task list into a Gantt chart with the critical path.

Try it: how far along is your checklist?

Tick the steps your team has closed with evidence in the tables above. The counts update as you tick. Nothing is sent or stored, and ticks are cleared when you leave the page.

Steps closed0 of 40
Phase 10 of 8
Phase 20 of 8
Phase 30 of 7
Phase 40 of 15
Phase 50 of 2

Priorities

Which steps matter most?

The steps that matter most are those that protect people or sit on the critical path: freezing the scope, finding the critical path, controlling isolations and permits, and the pre-startup review. 1,6

Not every step weighs the same. Rank open items by how much they threaten safety, scope, schedule or restart. A high-criticality pump overhaul on the restart path deserves more attention than a housekeeping task that can finish on its own. The sharper question is not how many work orders are done but which unresolved constraint could stop a safe, on-time restart.

A work package is ready only if it passes all six tests

Six readiness tests for each critical work package
TestThe question
ScopeIs the work clearly defined and approved?
PeopleAre qualified people available?
MaterialsAre all critical parts physically on site?
SafetyAre permits, isolations and risk controls ready?
MethodAre the procedures, drawings and job plans complete?
CompletionAre the inspection and acceptance criteria defined?

Visuals

Save the checklist charts

Two charts to pin up in the control room. Click either for the full-size image.

FAQ

Frequently asked questions

What is a shutdown checklist?

An ordered list of the controls a plant needs before, during and after a shutdown: scope frozen, work packaged, materials staged, isolations and permits controlled, and a safety review before restart. Each item has an owner, a timing and evidence of completion.

How many steps should a shutdown checklist have?

No public, vendor-neutral standard fixes a number. This guide uses 40 steps in five phases, which suits a large planned shutdown; a small shutdown can use the same phases with fewer steps.

When should the checklist start?

At the start of planning, because steps 1 to 8 settle the objective, the window, the scope and the critical path. How far ahead that is depends on the size of the stop. See how to plan a plant shutdown and how often a plant should shut down.

Does OSHA require a shutdown checklist?

No single checklist is required. For covered processes OSHA 1910.119 requires specific elements such as management of change, contractor controls, hot work permits and a pre-startup safety review, and 1910.147 covers lockout and tagout. 6,4

What is a pre-startup safety review?

A review before restart. Under OSHA 1910.119(i) it applies to new facilities and to modified facilities when the modification changes the process safety information, and confirms that construction, procedures and training are in place. Using it after routine maintenance is a site decision. 6

What is the difference between a checklist and a schedule?

The checklist says what must be true before work moves on and what evidence proves it. The schedule says when each activity runs and how activities depend on each other. The critical path comes from the schedule, not the checklist. 1 See shutdown scheduling.

Who owns the checklist?

The shutdown manager owns the checklist as a whole. Each step has a named owner, and the owners in this guide are typical, not mandatory.

What happens after restart?

Steps 39 and 40: monitor the plant for defects that only appear in operation, then record the lessons and update asset history, maintenance plans, job plans, checklists and the scope of the next stop. See learning and improvement.

Move your shutdown plan out of spreadsheets

Book a demo and bring the spreadsheet you use today. We will show how the module covers the same ground.

Book a demo