Shutdown audit

Shutdown Audit: Checklist, Findings and Inspections

Short answer

A shutdown audit checks whether the plan, the controls or the results of a stop meet a set standard. It comes in three kinds: a readiness audit before the stop, a compliance audit on a cycle and a performance review after restart. This guide gives a pre-shutdown checklist and the inspection regimes it touches.

How MaintWiz helps: Audits are faster when records, waivers and approvals are in one place. The MaintWiz shutdown module keeps handover notes, lessons learnt and deferred items with an archive of past shutdowns. See the module · Get the lessons register

By · Published · Last reviewed

What MaintWiz adds:Handover notesLessons learntDeferred itemsArchive of past shutdowns

Types

What does a shutdown audit cover?

A shutdown audit checks whether the plan, the controls and the results meet a set standard, and it comes in three kinds: a readiness audit before the stop, a compliance audit on a fixed cycle and a performance review after restart.

Update for India: the Occupational Safety, Health and Working Conditions Code, 2020 came into force on 21 November 2025 and subsumes the Factories Act, 1948. The Act sections quoted on this page now have corresponding duties in the Code, and the Centre and the states are still issuing rules under it, so confirm the current rule for your state before you plan work. 9,10

Three kinds of shutdown audit
AuditWhenQuestion it answersOutput
Readiness auditBefore the stop, after the scope freezeIs the plan complete and are we ready to start safely?Findings against the readiness tests; a go or no-go input
Compliance auditOn a fixed cycle, independent of the stopAre the required procedures and practices adequate and followed?Written report; documented response to each finding
Performance reviewAfter restartHow did the stop perform against plan, and why?Planned versus actual measures; lessons and actions

Each kind answers a different question. The readiness audit sits beside the readiness review in the 40-step checklist (step 23). The performance review feeds lessons learned and uses the measures in the KPI guide.

Checklist

What should a pre-shutdown audit check?

A pre-shutdown audit asks nine questions about scope, schedule, work packages, materials, people, isolation and permits, risk, emergency arrangements and restart, and for each it looks at the evidence, not the assurance.

The restart readiness and 40-step checklist workbooks are in the shutdown planning templates. For UK written schemes of examination see PSSR pressure systems safety regulations in the UK. A free Excel version is available: Audit checklist and findings log (.xlsx).

Readiness audit: questions and the evidence to see
AreaAudit questionEvidence to see
ScopeIs the scope frozen, with changes approved in writing?Baseline scope and a change log
ScheduleIs the schedule logic-linked, with the critical path and float known?Baseline schedule; critical-path list
Work packagesIs each package complete: steps, parts, tools, permits, acceptance?Packages sampled against the contents list
MaterialsAre critical parts physically on site?Material readiness report; bin checks
PeopleAre crews, inspectors and contractors confirmed and inducted?Resource-loaded plan; induction records
Isolation and permitsIs the isolation approach set and the permit matrix ready?Isolation plan; permit matrix; lockout procedures
RiskIs there a register with owners, triggers and contingencies?Risk register reviewed in the last cycle
Emergency and communicationDo people know the emergency arrangements and the daily rhythm?Emergency plan; meeting schedule
RestartAre the completion, testing and restart steps planned?Commissioning plan; pre-startup review plan

Sample the evidence rather than ask for statements. Open three work packages, two permits and the isolation plan and see whether they match. See also the work package guide, risk assessment guide and permit to work guide.

Software

Can software support shutdown audits?

Software helps an auditor see evidence quickly: gate results, waivers with reasons, readings and photos, and baseline changes sit in one record, with the name and time of every approval.

About MaintWiz. MaintWiz is an industrial AI platform with IoT, SAP integration and predictive maintenance (PdM) capabilities. Its shutdown and turnaround module helps plants plan, schedule, execute and close out shutdown work.

Also see the shutdown safety plan.

What the shutdown module covers

As described on the MaintWiz shutdown maintenance product page.

  • Readiness gates with waivers and sign-offs recorded with a reason, the name and the date
  • Baselines that show what moved against the plan
  • Work package tasks with readings, photos and out-of-spec flags
  • Handover note and as-left summary on each work order
  • Close-out, reports and archive of past shutdowns
  • Approvals recorded against the signed-in user with the name and the time

Findings

How do you act on shutdown audit findings?

Report every finding in writing, rate it, give it an owner and a date, and record how it was resolved; for US covered processes OSHA requires a documented response to each compliance audit finding and a record that deficiencies were corrected. 1

Rating audit findings (working scheme)
RatingMeaningRequired response
CriticalImmediate threat to people or to a safe restartStop the affected work or start; fix before it continues; report to the shutdown manager at once
MajorA required control is missing or not followedOwner and date; fix before the work it affects; verify
MinorA gap that does not weaken a control nowOwner and date; fix in the normal cycle
ObservationA good practice or an improvement ideaRecord; feed into lessons learned

Close findings with evidence, as with checklist steps: a sign-off, a test or a photo. Track open findings in the daily meeting during the stop.

Statutory inspection

Which statutory inspection regimes does a shutdown audit touch?

A shutdown audit should check that statutory and code inspections due in the stop are in scope, including OSHA compliance audits, UK written schemes of examination, API inspection codes and Indian boiler and pressure plant rules. 1,2,3

The Indian rows are expanded in annual shutdown planning in India and annual boiler shutdown in India. US permit conditions for treatment plants are in water and wastewater plant outages. For GMP requalification see pharmaceutical plant shutdowns.

Statutory and code inspection that shutdown audits often touch
RegimeWhereWhat it saysSource
Compliance audits, OSHA 1910.119(o)US, covered processesThe employer certifies that compliance has been evaluated at least every three years; a person knowledgeable in the process conducts the audit; a report is developed; findings get a documented response; the two most recent reports are keptOSHA 1910.119
Written scheme of examination, PSSR 2000UK, pressure systemsA suitable written scheme of examination must be in place before the system is operated, and the system must be examined in line with itHSE INDG178
API 510, in-service pressure vesselsUS and many other countries, as adoptedCovers in-service inspection, repair, alteration and rerating of pressure vessels; the edition that applies depends on what the owner or jurisdiction has adoptedAPI 510 summary
API 570, in-service pipingAs adoptedCovers in-service piping inspection; check the current editionAPI 570
API 653, aboveground storage tanksAs adoptedCovers steel storage tanks built to API 650 or API 12C; check the current editionAPI 653 summary
Factories Act 1948, section 31India, factoriesRequires effective measures to keep pressure plant within its safe working pressure; state rules govern examination and testing and vary by stateFactories Act 1948
Boilers Act 2025, section 12(6)India, boilersA boiler certificate authorizes use for a period not exceeding twelve months in the main case; the Act applies from a date the Central Government notifies, and commencement was not confirmed when this page was writtenBoilers Act 2025

The table lists regimes by country. It is not complete, and the list for your plant depends on your equipment, your jurisdiction and your insurer. Ask your inspection authority which examinations are due in each stop.

Visuals

Save the audit charts

Two charts to share with the audit team. Click either for the full-size image.

FAQ

Frequently asked questions

What is a shutdown audit?

A check that the plan, the controls or the results of a shutdown meet a set standard. It comes as a readiness audit before the stop, a compliance audit on a cycle and a performance review after restart.

How often is a compliance audit required?

For US covered processes OSHA 1910.119 requires a compliance evaluation at least every three years. 1 Other regimes set their own cycles.

Who should audit a shutdown?

Someone independent of the stop and knowledgeable in the process. For OSHA process safety compliance audits at least one person knowledgeable in the process must conduct the audit. 1

What should a pre-shutdown audit check?

Scope, schedule, work packages, materials, people, isolation and permits, risk, emergency arrangements and restart readiness, by looking at evidence. See the 40-step checklist.

What statutory inspections fall in a shutdown?

It depends on the equipment and the country: for example pressure vessels, piping and tanks under inspection codes, boilers and pressure systems under national law. 2,3,6 Ask your inspection authority.

What is a written scheme of examination?

A UK requirement for pressure systems: a suitable written scheme must be in place before the system is operated, and the system must be examined in line with it. 2

How do you close an audit finding?

With evidence: a sign-off, a test result or a photo, recorded against a named owner and a date. For OSHA covered processes the employer documents that deficiencies were corrected. 1

How is an audit different from lessons learned?

An audit tests against a standard; lessons learned look for what to change. Findings from an audit can become lessons. See shutdown lessons learned.