Pre-start-up testing

Hydrotest Planning After a Shutdown: Leak Test Register and Checks

Short answer

Hydrotest planning lists every repaired or reassembled system as a test pack, places the test late in the schedule with float for a leak, prepares each system and records the result and the reinstatement of every blind and gag. The code and your engineer set the test pressure and hold. MaintWiz holds test and reinstatement checks on the work order.

STO means shutdown, turnaround and outage. This page covers planning only; follow the applicable code, your engineer and your procedure for the test itself.

How MaintWiz helps: Tests come last, so any delay lands on the restart date. The MaintWiz shutdown module checks seven readiness gates before a package starts and records waivers with a typed reason, name and date. See the module · Get the test register

By · Published · Last reviewed

What MaintWiz adds:Seven readiness gatesSigned waivers with name and dateKeyboard operationLook-ahead by gate

Definition

What is hydrotest and leak test planning after a shutdown?

Hydrotest and leak test planning decides which repaired or reassembled systems need a strength test or a tightness test before restart, sequences the tests in the schedule, prepares each system, and records the result and the reinstatement of everything fitted for the test. In this guide STO means shutdown, turnaround and outage.

Repairs, alterations, new gaskets and replaced bundles all break the last proof that a system holds. The test is how you regain it. Tests come late in the schedule, so any delay or leak found there lands directly on the restart date. A planned register keeps them from becoming the surprise at the end of the stop.

This page covers planning. The test method, pressure and hold are set by the applicable code and your engineer; follow them. Download the free hydrotest and leak test register (Excel) to track every test pack.

Test types

What is the difference between a hydrotest and a leak test?

A hydrotest is a strength test that proves the pressure boundary at the pressure the code and engineer set, while a leak test proves joints are tight before start-up, and a pneumatic test is an exception that needs engineering approval because it stores much more energy.

Which test for which purpose
TestPurposePlanning note
Hydrostatic strength testProve the pressure boundary at the test pressure the code and engineer specifyUses water. Needs fill, vent, temperature and drain plans
Leak or tightness testProve joints and connections are tight before start-upOften at lower pressure. Method per procedure
Pneumatic testUsed only where water is not acceptableStores far more energy than a hydrotest. Needs engineering approval and a specific risk assessment
Pressure systems regulation checksExaminations required where regulations apply; see start-up after a shutdown 3Link the test to the written scheme where one exists

Pressure vessel and piping inspection codes such as API 510 and API 570 set requirements for tests after repair or alteration. Check the current edition. 1

MaintWiz

How does MaintWiz track pre-start-up tests?

MaintWiz puts test and reinstatement checks on the work order as checklists with readings and photos and holds the package closed until the permit and isolation are cleared; AI agents support shutdown planning.

Bring a test pack list to a demo and we will set it up as a checklist. Tell us what your inspectors sign: plant requirements shape what we build next.

About MaintWiz. MaintWiz is an industrial AI platform with IoT, SAP integration and predictive maintenance (PdM) capabilities. Its shutdown and turnaround module helps plants plan, schedule, execute and close out shutdown work.

What the shutdown module covers

As described on the MaintWiz shutdown maintenance product page.

  • Readiness gates that include tests and reinstatement
  • Permits and isolations shown on each work order
  • Checklists with readings and photos for technicians
  • Gantt chart with critical path, float and baselines
  • Findings from technicians sent straight to the planner
  • Handover notes and as-left summary

Plan

How do you plan hydrotests in a shutdown schedule?

Plan hydrotests by listing every repaired or reassembled system as a test pack, placing each test late in the sequence after repairs and before insulation or restart, adding float for leaks found, and booking the water, witnesses and exclusion zone ahead of time.

  1. 1

    List test packs

    One per system or equipment with its boundary and drawing.

    Register
  2. 2

    Get the approved pack

    Test type, pressure and hold from the engineer and code.

    Approval
  3. 3

    Place it in the schedule

    After repairs, before insulation and restart, with float for a failure.

    Sequence
  4. 4

    Book the resources

    Water supply, pump, gauges, witness and an exclusion zone.

    Resources
  5. 5

    Prepare the system

    Blinds, gagged relief valves, vents, drains, instruments isolated.

    Preparation
  6. 6

    Run, record, reinstate

    Test, drain, remove every fitting, restore, sign off.

    Close

Put tests that gate restart on the critical path view. See shutdown scheduling.

Checks

What should you check before a hydrotest?

Before a hydrotest confirm the approved test pack, list and fit the boundary blinds, gag or remove relief valves and record them, isolate instruments, confirm high-point vents and low-point drains, and make sure the water suits the materials and the metal temperature suits the procedure.

Checks before, during and after the test
WhenCheck
Before fillingApproved test pack in hand. Boundary blinds fitted and listed. Relief valves gagged or removed, and listed. Instruments isolated. Vents at high points and drains at low points confirmed. Water quality suitable for the materials
During the testExclusion zone set. Fill and vent. Check temperature of the metal against the procedure. Pressurize in steps. Hold as specified. Witness present
After the testDepressurize through the vents first. Drain and dry if required. Remove blinds. Restore relief valves and instruments. Update the register. Sign off

Reinstatement belongs in the restart check. See start-up after a shutdown 2.

Common misses

What goes wrong in turnaround pressure tests?

The common misses are a blind or gag left in after the test, a vent not opened so a vacuum forms on draining, trapped water that expands, unsuitable water for stainless materials, a test pack without an approved pressure and tests scheduled with no float for a leak.

Blind or gag left in

List every item fitted for the test and tick each one off at reinstatement.

Water problems

Wrong quality for the material, or trapped water that expands. Plan drains and quality.

No float

A leak found at the end moves the restart. Add float and a repair crew on standby.

No approved pack

Do not test to a pressure that is not in an approved pack.

Visuals

Save the pressure test planning visuals

Two visuals for the test coordinator. Click either for the full-size image.

FAQ

Frequently asked questions

What is a hydrotest?

A hydrostatic strength test that fills a system with water and raises it to the pressure the code and engineer specify to prove it holds.

What is the difference between a hydrotest and a leak test?

A hydrotest proves the pressure boundary at the specified test pressure. A leak test proves joints are tight before start-up, often at a lower pressure.

When is a pressure test needed after a shutdown?

After repairs, alterations, replaced components or reassembly that affect the pressure boundary, as the applicable code and your engineer require.

Where does a hydrotest sit in the shutdown schedule?

After the repairs and before insulation and restart, with float for a leak, and on the critical path where it gates restart.

Why avoid a pneumatic test?

A gas-filled system stores much more energy than a water-filled one. Use it only with engineering approval and a specific risk assessment.

What is the most common hydrotest mistake?

Leaving a blind or gagged relief valve in place after the test, so keep a list and tick off each one at reinstatement.

Who sets the test pressure?

The applicable code and the responsible engineer, recorded in the approved test pack.

Is there a free hydrotest register?

Yes. The hydrotest and leak test register (Excel) tracks each test pack, its preparations, the result and the reinstatement.

Does MaintWiz track tests before restart?

It holds test and reinstatement checks on the work order and keeps the package open until the permit and isolation clear. AI agents are part of the module. See AI shutdown planning.

Sources

Sources

This page gives planning practice and no test pressures. Use the code, your engineer and your procedure. API standards are listed on the API site; the OSHA and HSE pages cover pre-start-up review and pressure systems.

  1. American Petroleum Institute, Standards (API 510, 570 and 653 inspection codes are listed here)
  2. OSHA, 29 CFR 1910.119, Process safety management of highly hazardous chemicals
  3. UK Health and Safety Executive, Pressure Systems Safety Regulations 2000 (PSSR)

Start each package only when it is ready

Book a demo and bring a work package. We will walk through the seven readiness gates.