Skip to content
MaintWiz: Innovating Industrial AI

Cost estimating

Turnaround Cost Estimate: AACE Classes and Basis of Estimate

Short answer

A turnaround cost estimate is built at a stated AACE class, from Class 5 (concept) to Class 1 (check estimate), with a written basis and a separately held contingency. A Class 3 budget estimate typically carries -10% to -20% on the low side and +10% to +30% on the high side. MaintWiz tracks budget, actual and forecast cost against the estimate you approve.

STO means shutdown, turnaround and outage. The class ranges are typical figures from the AACE process-industry practice, not guarantees.

How MaintWiz helps: An estimate without a basis cannot be reviewed or updated. The MaintWiz shutdown module tracks earned value, cost and schedule indices and shows budget, actual and forecast cost in one view. See the module · Get the estimate template

By · Published · Last reviewed

What MaintWiz adds:Earned value and cost indicesBudget, actual and forecast costCost by project and packageCumulative spend

Definition

What is a turnaround cost estimate?

A turnaround cost estimate is the forecast of labor, materials, equipment, services and owner costs for the stop, plus contingency, built at a stated level of scope definition and written with a basis that lets someone else review it. 3

The same stop is estimated several times. The first figure, made when the scope is a list of ideas, is a rough range. The last, made when packages are issued, is tight. The AACE estimate class names that level of definition so that everyone reads the number the same way. In this guide STO means shutdown, turnaround and outage.

Download the free basis of estimate template (Excel) for a basis sheet, estimate lines with contingency and the typical range for the class you choose.

Estimate classes

What are the AACE estimate classes?

AACE International classifies estimates from Class 5 to Class 1 by how much of the project is defined, from concept screening at 0% to 2% definition with a very wide range to a check estimate at 65% to 100% definition with a narrow one. 1,2

AACE estimate classes for the process industries
ClassTypical useMaturity of definitionTypical low rangeTypical high range
5Concept screening0% to 2%-20% to -50%+30% to +100%
4Study or feasibility1% to 15%-15% to -30%+20% to +50%
3Budget authorization10% to 40%-10% to -20%+10% to +30%
2Control or bid30% to 75%-5% to -15%+5% to +20%
1Check estimate or bid65% to 100%-3% to -10%+3% to +15%

Maturity of definition is what sets the class. The ranges are typical for the process industries and depend on the quality of the estimating and the risk, so treat them as a guide for your own history, not as a promise.

Map the class to your gates. As our assessment, a stop at scope-defined is usually a Class 4 estimate, at plan approval a Class 3, and after the scope freeze a Class 2. See readiness gates.

MaintWiz

How does MaintWiz track the estimate against actual cost?

MaintWiz keeps the budget, actual and forecast cost with earned value, cost and schedule indices by project and package, so the estimate you approved is compared with spend every day; AI agents support shutdown planning.

Bring your last estimate to a demo and we will load it as the baseline. Tell us how you hold contingency: plant requirements shape what we build next.

About MaintWiz. MaintWiz is an industrial AI platform with IoT, SAP integration and predictive maintenance (PdM) capabilities. Its shutdown and turnaround module helps plants plan, schedule, execute and close out shutdown work.

What the shutdown module covers

As described on the MaintWiz shutdown maintenance product page.

  • Budget, actual and forecast cost in one view
  • Earned value, cost and schedule indices
  • Cost by project and package
  • Cumulative spend
  • Baselines show what moved
  • Findings from technicians sent straight to the planner

Basis of estimate

What is a basis of estimate?

A basis of estimate is the written record of how the estimate was made: scope, ground rules, assumptions, exclusions, quantities, rates and quote sources, allowances, contingency method, escalation, class and reviewer, so that the number can be checked and updated. 3

What a basis of estimate contains
SectionWhat to write
Scope and ground rulesWhat is in and out, work hours, shifts, calendar, owner-supplied items
Assumptions and exclusionsAccess, productivity, weather, permits, anything not priced
Quantities and methodUnit-rate from past stops, factored, or bottom-up from work packages
Rates and quotesLabor rates, contractor quotes, material prices, dates and sources
AllowancesWhat is covered by a lump allowance and why
ContingencyMethod, amount and who may release it
EscalationPrice changes between estimate date and execution
Class, date and reviewerEstimate class, version, estimator and reviewer

Write the basis while you estimate, not after. When the stop overruns, the basis shows whether the estimate was wrong or the scope changed.

Breakdown

How do you break down a turnaround cost estimate?

Break a turnaround estimate into direct labor, supervision and indirect costs, materials and spares, equipment, scaffold and insulation, inspection and testing, services, engineering and owner costs, and contingency, each with its own source.

Cost breakdown for a turnaround estimate
Cost groupIncludesCommon source
Direct laborTrades on the work packagesPackage hours × rate
Supervision and indirectSupervisors, planners, safety, site servicesRatio from past stops
Materials and sparesParts, gaskets, fasteners, consumablesBill of materials and quotes
EquipmentCranes, hydroblasters, lifts, temporary powerHire quotes and duration
Scaffold, insulation, coatingAccess and finishing tradesScaffold register; see scaffolding planning
Inspection and testingNDE, hydrotest, third-party inspectorsInspection plan
ServicesCleaning, waste, catalyst handlingContractor quotes
Engineering and owner costsDesign, project team, permitsBudget lines
ContingencyAllowance for emergent and uncertain workMethod in the basis

Link the breakdown to the budget. See shutdown budget planning and cost variance analysis.

Contingency

How much contingency should a turnaround estimate carry?

Set turnaround contingency from your own past overruns and from a risk review of the scope, hold it separately from the base estimate, and name the person who can release it; the amount should fall as the class improves. 4

  1. 1

    Price the base scope

    Quantities and rates, with no padding.

    Base
  2. 2

    Add allowances

    For known work not yet defined, such as insulation.

    Allowances
  3. 3

    Review the risks

    Emergent work, access, weather, supplier delays.

    Risk
  4. 4

    Size contingency

    Use past stops: how much did emergent work add?

    History
  5. 5

    Hold and release

    One owner; releases are logged with a reason.

    Control

Emergent work is the usual reason a stop overruns. See scope management and why shutdowns go over budget.

Visuals

Save the cost estimating visuals

Two visuals for the estimating team. Click either for the full-size image.

FAQ

Frequently asked questions

What is an AACE estimate class?

A label from Class 5 to Class 1 that shows how much of the project is defined when the estimate is made. Less definition means a wider range. 1

What is a Class 3 estimate?

A budget authorization estimate, made at about 10% to 40% project definition, with a typical range of -10% to -20% low and +10% to +30% high. 1

What is a basis of estimate?

The written record of scope, assumptions, rates, quantities, contingency method, class and reviewer that lets someone else check and update the number.

How much contingency does a turnaround need?

It depends on scope maturity and history. Set it from your own past overruns and a risk review, and reduce it as the class improves.

What class should a turnaround estimate be at each stage?

Our assessment: Class 4 at scope defined, Class 3 at plan approval and Class 2 after scope freeze. Check against your company practice.

What is the difference between allowance and contingency?

An allowance covers known work not yet defined. Contingency covers uncertainty and emergent work. Keep them separate in the basis.

How do you estimate turnaround labor?

Take hours from the work packages, convert to people with shift hours and time on tools, and price by trade rate.

Is there a free turnaround estimate template?

Yes. The basis of estimate template (Excel) has a basis sheet, estimate lines with contingency and the typical range by class.

Does MaintWiz track estimates against actual cost?

It tracks budget, actual and forecast cost with earned value and cost and schedule indices. AI agents are part of the module. See AI shutdown planning.

See cost and schedule performance in one view

Book a demo and bring your shutdown budget. We will show earned value and forecast cost in the module.

Book a demo